5: Readiness for next phase: Readiness for service
Contents
Resource information
http://www.ssc.govt.nz/copyright
|
Areas to probe |
Evidence expected |
|
5.1 Is the working relationship likely to succeed? |
· Realistic assessment of management style/behaviours on both sides · Reporting arrangements identified at appropriate levels on both sides · Suitable procedures and responsibilities for contract management are defined and agreed · For construction projects, plans for integrating the Project Team · Continuity of key personnel from the contract award phase into the implementation phase. |
|
5.2 Are all resources and internal funds (the 'client-side budget') in place? |
· Budget provision · Manpower provision agreed · Subsequent years' expenditure included in programme or project budgets · Authorisation/approval process for payments to suppliers · Process for expenditure reporting and reconciliation · Insurances established by supplier where required. |
|
5.3 Are the supplier's project, risk and management plans adequate and realistic? |
· Confirmation that the supplier's or partner's project plan meets timescales for achieving the outcome of the investment · Realistic supplier's or partner's implementation plan and plans for managing risk. |
|
5.4 Does the client-side plan reflect the supplier's plans, and vice versa? |
· Updated project management plan reflecting tender proposals · Defined organisation, personnel and responsibilities on the client's side · Supplier personnel cleared to meet project requirements · Process for resolving issues agreed with supplier/partner · Evidence that all plans have been reviewed, agreed and included in the contract. |
|
5.5 Are the long-term contract administration plan and benefit measurement process complete? |
· Long-term plan with contract management strategy and a detailed service delivery plan · Resources, with identified sources · Key measures of benefit agreed with supplier/partner (if supplier payments related to benefits delivery) · Analysis of project plan showing that resource requirements are identified, planned, budgeted for and available when required · Defined roles and responsibilities. |
|
5.6 Are all the mechanisms and processes in place for the next phase? |
· Project Plan confirms arrangements for management, monitoring, transition and implementation · If external consultants are used, they are accountable and committed to help ensure successful and timely delivery. |
|
5.7 Are the service management plan, administration and service level arrangements complete? |
· Documented service management strategy and plan · Defined and agreed service level management, service levels, service quality and measurement · Responsibilities defined for each party · Defined and agreed standards for services · Defined and agreed monitoring, reporting and review mechanisms. |
|
5.8 Is the management process for service change complete? |
· Change control procedures (both technical and business) defined, agreed and included in contract · Defined and agreed management process and responsibilities. |
|
5.9 Is there an acceptance strategy or commissioning strategy, as applicable? |
· Acceptance/commissioning strategy and plan, with fully documented and timetabled decision paths (e.g. for preferred supplier choices) · Decision makers clearly identified and informed about their role and what information they will be given to make their judgement · Acceptance criteria agreed with supplier · Validated acceptance testing plan, including technical and business components. |
|
5.10 Is there an implementation strategy? |
· Implementation strategy and plan · Users, stakeholders and client business management involved in developing strategy · Where applicable, plans for transition to new ways of working · Clearly defined roles on client and supplier sides for monitoring and controlling handover. |