2: Business Case and stakeholders
Contents
Resource information
http://www.ssc.govt.nz/copyright
|
Areas to probe |
Evidence expected |
|
2.1 Is the project still required? |
· Confirmation that the project still fits with strategic objectives, including government/organisational objectives · Confirmation that external factors have not affected current priorities. |
|
2.2 Is the Business Case complete? |
· Re-assessment of updated Business Case, including strategic, economic, financial, commercial and project management factors. |
|
2.3 Does the recommended way forward meet the business need? |
· Key objectives revisited against final bid and proposed solution. |
|
2.4 Has the most appropriate option been selected? |
· Cost/benefit/risk analysis against final bid information and results of evaluation, including sensitivity analysis · For construction projects, whole-life design quality, cost and time optimised as far as possible. |
|
2.5 Does the commercial arrangement represent value for money, with an appropriate level of quality over the whole life of the project? |
· Market assessment, other organisational benchmarks and previous experience · Results of evaluation (note that clients with existing commercial arrangements must address this area) · Where appropriate, assessment of supplier's funding arrangements. |
|
2.6 Is the client realistic about their ability to manage the change? |
· Documented understanding of cultural implications, where appropriate; account has been taken of the current organisational culture · Comparison with others. |
|
2.7 Does the Detailed Business Case, when incorporating the delivery solution, still demonstrate affordability? |
· Detailed Business Case incorporating bid information, including: o changes from budgetary figures o returns and value re-calculated with new benefits plan o costs compared with budget, pre-tender estimates. |
|
2.8 Is there an agreed benefits realisation plan? |
· Benefits management strategy and plans including: o critical success factors o individuals responsible for delivering and achieving benefits identified o agreed process for measuring and assessing benefit o data available on measurement baselines for benefits assessment o post-implementation review plan identifies review points and benefits to be assessed; payment mechanisms linked to benefits realisation, where appropriate. |
|
2.9 Have suitable stakeholders, business and user representatives been involved and have they approved the tender evaluation report and draft contract? |
· Involvement of stakeholders and business or user representatives in quality and proposal reviews · The views of all stakeholders, including users, have been taken into account · Representation on the Evaluation Team · Approval by Project Board or steering group. |